# Working together

> How you and your delivery team work together during a migration, how the work is validated, and how it is signed off.

Once your systems are connected, you and your delivery team work together until the migration is signed off. Collaboration and validation run through the whole project, not only at the end.

## How you work together

* **A shared channel and regular syncs** with the people on your side who can make decisions. Your delivery team shares progress and open questions there.
* **Pull requests in your repository.** Migrated code arrives as pull requests, each with the validation evidence for the objects it contains. Reviewing them before merge is your choice.
* **Decisions in writing.** You decide questions about business logic, and any place where the new code should behave differently from the old. Each decision is recorded.

## What your team provides

| What's needed | Why it matters |
| :- | :- |
| **Answers on business logic**, such as legacy bugs to keep or fix, unclear rules and undocumented edge cases | An open question blocks every object that depends on the answer. |
| **Coding standards agreed at the start**: naming, project structure, and materialization and orchestration patterns | Standards raised late mean reworking code that was already delivered. |
| **Reviews, merges and deployments that keep up** | Work that waits on review, merge or deployment holds up the work behind it. |
| **Production-quality data for validation**: production itself, or a lower environment with production-quality data | Validation on sample or synthetic data isn't meaningful, and the work usually has to be redone once real data arrives. |
| **Access that stays working**: service users, SSO, keys and CI credentials don't expire or rotate without notice | A credential that stops working holds up everything behind it. |

If the scope changes, or legacy code changes during the migration, tell your delivery team as early as possible. A refactor or redesign that isn't in your contract is a change of scope. It needs a change to the contract before any of it is done, not only an agreement with your delivery team.

## Validation

Every object in scope is validated against your legacy system. Data diffs are one of the tools your delivery team uses for this: a data diff compares two tables and shows which rows, columns and values differ. Validation is part of the work from the first delivery, not a QA phase at the end.

Some differences are expected and don't mean the migration is wrong. Some are changes your contract includes as part of modernizing. Others come from the systems themselves, which may load data at different times or round numbers differently. Where an object doesn't fully match, your delivery team explains the difference and recommends accepting it or fixing it. You decide.

To understand a specific result, ask the Datafold assistant in the app, or ask in your shared channel.

## Sign-off and handover

You and your delivery team agree what done means before work starts. Sign-off is then a check against evidence that has built up over the whole project.

Deployment to production and user acceptance testing (UAT) in your environment are yours unless your contract says otherwise. Your delivery team supports you through both.

At the end of the project you have the code in your repository, the validation evidence, and the documentation to operate it. You own the code from the moment it's delivered. It runs on your target platform with no runtime dependency on Datafold.